Specifications | |
No. of Floors | 2 |
Single-story factory area | 1800-3000 m2 |
Number of transformers | 3/4/5/6 |
Single factory power capacity | 9-18 MW |
Rack quantity | 45-90 |
Miners capacity | 5400--10800 |
Single load reference cost | 420,000RMB/MW |
Single machine reference cost | 550-650 RMB |
Standardized system:
1. Rack standardized design (standardization of external dimensions, standardization of structural combination)
2. Standardization of hot and cold channels (dividing hot and cold channels between racks, one side of the rack is a cold aisle, the other side is a hot aisle, and the hot and cold channels are isolated)
3. Standardization of cooling system (natural cooling - water evaporative cooling, standardized configuration of water circulation system)
4. Standardization of electrical system (modulation of electrical system, each module is independent of each other to ensure a stable and reliable system.)
5. Standardization of two-story buildings (standardization of building shape, layout, and structure)
Second Floor Plan (with 6 transformers)
Elevation
Sectional view
Note: the information provided on the website may be used as general reference only. Please read our disclaimer here.